Muswellbrook Bridges Replacement -outside of normal hours construction work-community notice April 6:30am Tuesday 27 April to 6:00pm Friday 30 April.

Please note: construction will continue during standard construction hours outside of this period

857_April Shutdown Notification Flyer_v1_210315_QR code

.....................................................................................................

March 2021

    From April 6 to April 9 there will be works to the following at Bridge Street bridge.
  • Construction of concrete Pilecaps at Bridge St – Day and Night works. Essentially just steel fixing, formwork installation and concrete pours.
  • Construction of our casting yard for Muscle Ck and Hunter River Bridge – Day works only.
  • Piling works for Muscle Ck and Hunter River Bridge – Day works only. Note that the works will not impact traffic.

Click the link below for more information: 

857-April-Shutdown-Notification-brochure8

.....................................................................................................

February 2021

From June 2020, Australian Rail Track Corporation (ARTC) is replacing three existing rail bridges in Muswellbrook for the purpose of improving rail network reliability.

The project involves replacement of the existing bridges spanning Bridge St, Muscle Creek and Hunter River.  The Bridge St structure will be replaced with a 26 metre long single span concrete bridge, with the Muscle Creek and Hunter River Bridges replaced with a combined 175 metre long multi span concrete bridge.

This project is planned to be complete by June 2022.

6:30am Tuesday 9 February to 6:00pm Friday 12 February
For more information please contact 1300 550 402 (24 hours) or email This email address is being protected from spambots. You need JavaScript enabled to view it.

Click the link below for more information: 

857_February Shutdown Notification Flyer_V1_210118

.....................................................................................................