About the Project
Muswellbrook Shire Council will commence its road resealing program in various locations around the Shire from mid-October 2023, weather permitting. Council has engaged Contractors Fulton Hogan Australia (Management) Pty Ltd to carry out the work.
Increasing the frequency with which Council reseals roads leads to greater protection of the underlying pavement, which in turn prevents deterioration and maximises the lifespan of the road.
Apart from the bitumen sealing of the road, the works will also include any preparatory works such as weed spraying, pothole patching, shoulder preparation and heavy patching.
Proposed Schedule - Week Commencing 23/10/2023
Job Location | Seal Type | Estimated Area (m2) | |
---|---|---|---|
23 October 2023 | Widden Valley Road 10km to 13.580km | 14mm reseal | 21,480 |
24 October 2023 | Rosemount Road 0km to 0.365km | 10mm reseal, 7mm scatter | 3,650 |
Rosemount Road 0.365km to 1.30km | 14mm reseal | 6,750 | |
25 October 2023 | Rosemount Road 3km to 4.95km | 14mm reseal | 16,990 |
26 October 2023 | DENMAN Turner Street, Jerdan Street, Babbington Street, Burkill Street | 10mm reseal | 6,872 |
27 October 2023 | MUSWELLBROOK Cousins Street, Queen Street | 10mm reseal | 9,864 |
Proposed Schedule - Week Commencing 13/11/2023
Date | Location | Estimated Area (m2) |
---|---|---|
13 November 2023 | CORAL STREET from Tobruk Avenue to the end | 1,190 |
QUEEN STREET from Mataro Avenue to Lexia Street | 7,056 | |
14 November 2023 | TRAMINER STREET from Shiraz Street to Riesling Street | 1,338 |
COUSINS STREET from Barrington Street to Claret Avenue | 2,808 | |
WILKINS STREET from Ford Street to Aberdeen Street | 1,500 | |
15 November 2023 | WEEMALA PLACE from Bloodwood Road to seal change | 1,418 |
FORD STREET from Wilkins Street to the end | 1,063 | |
20 November 2023 | MARTINDALE ROAD from 6.91km to 7.25km | 2,768 |
SANDY CREEK ROAD from 10.39km to 10.74km | 2,975 | |
21 November 2023 | THOMAS MITCHELL DRIVE from 6.46km to 7.895km | 17,220 |
22 November 2023 | THOMAS MITCHELL DRIVE from 8.12km to 9.46km | 16,080 |
Program Update 15/01/2024
The Shire Road Resealing Program has kicked off again this week with asphalt corrective sealing in Hill Street and King Street, Muswellbrook. These works were programmed to occur outside of school times to mitigate impacts and undertake the work in the safest possible way, due to their proximity to local schools.
Preparatory works to repair failed sections of pavement, prior to upcoming bitumen sealing, will continue next week on various sections of Sandy Creek Road.